F.




Steel Falsework Construction





































1.

Are steel structural shapes and plates identified by ASTM number on the falsework plans and in the calculations?




____

____

____

























2.

Have steel beams been checked for bending, shear, web crippling and buckling of the compression flange?




____

____

____

























3.

Has horizontal plane bracing been shown where required to limit compression flange buckling?




____

____

____






















G.




Deflections and Settlement





































1.

Is falsework deflection for concrete dead load shown on the plans for all falsework spans?




____

____

____

























2.

Is falsework deflection from concrete dead load limited to 1/240 of the span length for all falsework spans?




____

____

____

























3.

Do stringers supporting cast-in-place concrete compensate for estimated camber?




____

____

____

























4.

For beam spans with cantilevers, has the upward deflection of the cantilevers due to load placed on the main spans been investigated?




____

____

____

























5.

Are provisions shown for taking up falsework settlement?




____

____

____






















H.




Compression Members, Connections and Bracing





































1.

Has general buckling been evaluated for all compression members?




____

____

____

























2.

Has bracing been provided at all points of assumed support for compression members?




____

____

____

























3.

Was bracing in each direction considered in establishing the effective length used to check post capacity?




____

____

____

























4.

Is bracing strength and stiffness sufficient for the intended purpose?




____

____

____

























5.

If temporary bracing is required during intermediate stages of falsework erection, is it shown on the falsework plans?




____

____

____

























6.

Have all connections been designed and detailed?




____

____

____

























7.

Are web stiffeners required on steel cap beams to resist eccentric loads?




____

____

____

























8.

Are wedges required between longitudinal beams and cap beams to accommodate longitudinal slope or to reduce eccentric loading?




____

____

____

























9.

Has the width to height ratio of wedge packs been verified to fall within the limits given in the special provisions?




____

____

____

























10.

If overhang brackets are attached to unstiffened girder webs, has the need for temporary bracing to prevent longitudinal girder distortion been investigated?




____

____

____

























11.

Have beams and stringers with height/width ratios greater than 2.5:1 been checked for stability?




____

____

____

























12.

Have sloping falsework members that exert horizontal forces on the falsework been braced or tied to resist these loads?




____

____

____

























13.

If beams supporting cast-in-place concrete have cantilever spans, have the falsework plans been noted to require the main spans be loaded before loading the cantilever spans?




____

____

____

























14.

Have timber headers set on shoring towers been checked for eccentric loads, and for shear and bending stresses produced by the eccentricity?




____

____

____






















I.




Highway and Railroad Traffic Openings (for falsework over or adjacent to highway or railroad traffic openings)





































1.

Do falsework plans satisfy construction clearances shown on the contract plans?




____

____

____

























2.

Are posts designed for 150% of the calculated vertical loading and increased or readjusted for loads caused by prestressing forces?




____

____

____

























3.

Are mechanical connections 2,000 lbs. minimum capacity shown at the bottom of posts to footing connections?




____

____

____

























4.

Are mechanical connections 1,000 lbs. minimum capacity shown at the top of the post to cap connections?




____

____

____

























5.

Are beam tie downs 500 lbs. minimum capacity shown for all beams?




____

____

____

























6,

Are 5/8 inch or larger diameter bolts used at connections for timber bracing?




____

____

____

























7.

Are temporary erection/removal bracing shown?




____

____

____