Audit Clause
The Government will provide the Resident Representative with certified periodic financial statements, and with an annual audit of the financial statements relating to the status of UNDP (including GEF) funds according to the established procedures set out in the Programming and Finance manuals. The Audit will be conducted by the legally recognized auditor of the Government, or by a commercial auditor engaged by the Government.
3. Learning and Knowledge Sharing
Results from the project will be disseminated within and beyond the project intervention zone through a number of existing information sharing networks and forums. In addition:
-
The project will participate, as relevant and appropriate, in UNDP/GEF sponsored networks, organized for Senior Personnel working on projects that share common characteristics. UNDP/GEF shall establish a number of networks, such as Integrated Ecosystem Management, eco-tourism, co-management, etc, that will largely function on the basis of an electronic platform.
-
The project will identify and participate, as relevant and appropriate, in scientific, policy-based and/or any other networks, which may be of benefit to project implementation though lessons learned.
The project will identify, analyze, and share lessons learned that might be beneficial in the design and implementation of similar future projects. Identify and analyzing lessons learned is an on- going process, and the need to communicate such lessons as one of the project's central contributions is a requirement to be delivered not less frequently than once every 12 months. UNDP/GEF shall provide a format and assist the project team in categorizing, documenting and reporting on lessons learned. To this end a percentage of project resources will need to be allocated for these activities.
Table G-1 : Indicative Monitoring and Evaluation Work plan and corresponding Budget
Type of M&E activity
|
Responsible Parties
|
Budget US$
Excluding project team Staff time
|
Time frame
|
Inception Workshop
| -
Project Coordinator
-
UNDP CO
-
UNDP GEF
|
|
Within first two months of project start up
|
Inception Report
| |
None
|
Immediately following IW
|
Measurement of Means of Verification for Project Purpose Indicators
| -
Project Coordinator will oversee the hiring of specific studies and institutions, and delegate responsibilities to relevant team members
|
To be finalized in Inception Phase and Workshop. Indicative cost XXXX
|
Start, mid and end of project
|
Measurement of Means of Verification for Project Progress and Performance ( measured on an annual basis )
| |
To be determined as part of the Annual Work Plan's preparation. Indicative cost xxxx
|
Annually prior to APR/PIR and to the definition of annual work plans
|
APR and PIR
| -
Project Team
-
UNDP-CO
-
UNDP-GEF
|
None
|
Annually
|
TPR and TPR report
| |
None
|
Every year, upon receipt of APR
|
Steering Committee Meetings
| -
Project Coordinator
-
UNDP CO
|
None
|
Following Project IW and subsequently at least once a year
|
Periodic status reports
| |
5,000
|
To be determined by Project team and UNDP CO
|
Technical reports
| -
Project team
-
Hired consultants as needed
|
15,000
|
To be determined by Project Team and UNDP-CO
|
Mid-term External Evaluation
| -
Project team
-
UNDP- CO
-
UNDP-GEF Regional Coordinating Unit
-
External Consultants (i.e. evaluation team)
|
20,000
|
At the mid-point of project implementation.
|
Final External Evaluation
| -
Project team,
-
UNDP-CO
-
UNDP-GEF Regional Coordinating Unit
-
External Consultants (i.e. evaluation team)
|
30,000
|
At the end of project implementation
|
Terminal Report
| -
Project team
-
UNDP-CO
-
External Consultant
|
None
|
At least one month before the end of the project
|
Lessons learned
| |
15,000 (average 3,000 per year)
|
Yearly
|
Audit
| |
4,000 (average $1000 per year)
|
Yearly
|
Visits to field sites (UNDP staff travel costs to be charged to IA fees)
| -
UNDP Country Office
-
UNDP-GEF Regional Coordinating Unit (as appropriate)
-
Government representatives
|
15,000 (average one visit per year)
|
Yearly
|
TOTAL indicative COST
Excluding project team staff time and UNDP staff and travel expenses
|
US$ 250,00036
|
|
Annex G-2: Impact Measurement Template
(These indicators will be drawn from the Logframe Matrix and are related to the measurement of global benefits achieved by the project rather than project implementation progress. They will to be fine tuned and detailed in the Inception Workshop). The table below is an example.
Key Impact
Indicator
|
Target
(Year 4)
|
Means of Verification
|
Sampling frequency
|
Location
|
Km2 of stable xxx forest cover
|
xxxx forest cover in 86,289 km 2 has not decreased since project start
|
Satellite imagery
|
Start, mid,end
|
All PAs
|
% decrease of energy derived from unmanaged forest
|
The percentage of the energy derived from unmanaged Caatinga forest in areas covering 86,289 km2 of the biome has been reduced 25%
|
Survey of forest product consumption
|
Start, mid,end
|
All PAs
|
xx Hectares of xxx forest under sustainable wood production
|
3,143 km2 of xxxx forest are under sustainable wood production
|
register of sustainable production plans
|
Start, mid,end
|
xxxxx
|
Number hectares under protection
|
An additional 7,000 hectares of xxx have been placed under protection in Private Reserves and Biological Reserves
|
reports
|
Annually
|
xxxxxx
|
Populations of Indicator species
|
Populations of fauna indicator species in corridors remain stable or have increased. These species will be selected during the inception phase
|
Fauna inventories
|
Start, mid,end
|
xxxxx
|
Carbon sequestration
|
Tons of carbon sequestered per hectare in xxx hectares of project zone
|
Ground sampling and satellite imagery
|
Start, mid,end
|
Target zone
|
Soil erosion on xxx hectares
|
Tons of reduction in sedimentation of key waterways; hectares of land restored
|
Ground sampling; reports
|
Start, mid,end
|
Target zone
|
|