63. No extra payment will be made to the executing agency for excess consumption of material beyond the norms.

64. CHANGES IN COST OF BITUMEN


Clause 1

Increase or

Decrease of cost

These shall be added to or deducted from the contract price such sum in respect of rise or fall in the cost of bitumen affecting the cost of the execution of work as may be determined by the Engineer-in-charge

Clause 2

Base and current Prices

The base cost price shall be those taken in the analysis of rates . Current prices shall be those mentioned in the actual invoice of bitumen to be produced by the contractors during the period to which a running bill is related.

Clause 3

Price Adjustment (A)

The price adjustment shall be the amount payable to the contractor valued at base cost price and current price in the running bill prepared by the Engineer pursuant to clause-1 here in respect of rise or fall in the cost of bitumen.




(B)

To the extent of compensation to cover the contingency for rise or fall of cost of bitumen to be consumed in bulk quantity or otherwise mentioned in the tender document.




( C )

The price adjustment shall be the evaluated for the relevant rate of each running bill approved by the Engineer pursuant to clause-1 using the weight age related to the current and base cost price.

Clause 4

Adjustable

The adjustment amount shall be the difference between the amount due to the contractor in pursuant to clause-1 and the amount in respect to bitumen in the running bill.

Clause 5

Limit of price adjustment

Provided that in determining price adjustment of bitumen in accordance with aforesaid clauses No account will be taken of any amount by which any cost incurred by the contractor has been increased by default or negligence of the contractor.


Executive Engineer (C),

Punjab Mandi Board,

ANNEXURE
AND
FORMS


ANNEXURE -1

(See Clause)

List of essential equipment and machinery to be arranged by the contractor free of cost
(As reqd. according to nature of work to be decided by Engineer in charge)
a) For construction
1. Steel shuttering _________________________ Sqm. 2. Concrete mixer with hoppers _________________________ Nos.
3. Concrete Vibrators _________________________ Nos.
4. Pump sets _________________________ Nos.

5. G.I. Pipeline with specials __________________________ Meters

6. Flexible pipeline _________________________ Meters

7. Theodolite ______________________ Nos
8. Dumpy level with leveling staves _________________________ Nos
9. Plane table set _________________________ Nos
(b) For field laboratory
1. Compression testing machine _________________________ Nos
2. Concrete cube moulds 150x250x150mm _________________________ Nos
3. Slump cones _________________________ Nos
4. Graduated cylinder _________________________ Nos
5. Set of sieves for coarse aggregate _________________________ sets

(40,20,10 & 4.75) m.m.
6. Set of sieves for fine aggregate

(10,4.75,2.36,1.18 mm. & 600,300,150 micron) _________________________ sets

7. Weighing scale (pan type) with weights _________________________ Nos

8. Core-cutters for soil with accessories _________________________ Nos
9. Electronics Moisture meter for timber _________________________ Nos
10. Latest B.I.S. codes for wood work. Flooring, Masonry,

Marble flooring, concrete work, aggregates and other

Important items. _________________________ Nos
11. Measurement Box _________________________Nos

ANNEXURE – E
All the material like Bitumen, Cement, steel and Hum pipes etc. are to be arranged by agency himself and payment for these items are based on documentary evidence in the shape of invoices from the approved agencies as per chart given below :-
MATERIAL BRAND CHART
1. Cement : OPC 43 grade conforming to IS 8112: or PPC confirming

IS: 1489 (part-1) such as Ambuja, ACC, Vikram, K,Luxmi,

Binani etc.with the approval of the concerned Engineer

in-charge.
2. Steel : Fe 415 grade CTD or TMT bars conforming to IS 1786

Such as Tata ,sale,Tisco,Rashtrya Ispat Nigam etc. with

the approval of the Engineer-in-charge
3. Structural steel: Structural steel such as angle section T-section , I ection ,

channel and steel plate shall be conforming to 1S:226
4. Bitumen: VG-10/VG-30 Bitumen from IOC/HPCL/BPCL conforming

to IRC -73-2006
5. Hume Pipes: NP3 with ISI mark with the approval of the Engineer-in-charge.
6. Any other item. All other materials required for the construction shall

conform to Punjab PWD Specifications or latest ISI

specifications depending upon the product. The decision

of the Engineer-in-charge shall be final.

7. Rs.----------- per M.T have been taken as supply rate for bitumen grade VG-

10/VG-30(as applicable) in the analysis of the rates .
Note:


  1. The department will be at liberty to take samples from such material and get tested from an approved laboratory at the cost contractor and the material shall be allowed to be consumed only , if these conducted tests are in order.




  1. As all the material are to be arranged by the contractor , the relevant clause in the agreement /DNIT relating to stores to be issued by department will not be applicable.

3) The test report of material supplied by the contractor/agency will be provided before its use.

4) Instruction issued from Chief Engineer PB PWD. ( B&R ) Patiala vide Memo No. 2816-28/RI dt. 30/7/04 will be followed strictly.

SPECIMEN

A FORM OF PERFORMANCE BANK GUARANTEE

To

Name of Employer …………..................................................................................................

Address of Employer .................................................................................................................
WHEREAS (Name and Address of contractor) ........................

(hereinafter called” the contractor”) has undertaken, in pursuance of contract No. ........................

dated ; to execute (Name of contract and brief description of

works) “ called “the contract”.

AND WHEREAS we have agreed. to give the Contractor such a Bank Guarantee.
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on ‘behalf of the Contractor, upto a total amount of Guarantee ........................................................................................

(in words) “ we undertake to pay you, upon your first written demand and without. cavil or argument, any sum or sums within the limits of amount of Guarantee as aforesaid without your needing to prove or to show grounds or reasons for your demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the contractor before presenting us with the demand.
We further agree that no change or addition to or other modifications of the terms of the contractor of the works to be performed there under or any of the contract documents which may be made between you and the contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such change. addition or modification.

This guarantee is valid until the date months after the issuing of the maintenance. certificate.

SIGNATURE AND SEAL OF THE GUARANTOR ........................................
Name of Bank .........................................
Address .........................................
Date ...........................................

ESTIMATED COST

AND

BILL OF QUANTITIES
BILL OF QUANTITIES

Name of Work_________________________________________
Time Limit _____________________



S No

Description of Item

Quantity

Unit

Rate

Amount






























































































































































































































































































































































































Total Amount (“A”)





Rate to be quoted by the Contractor:

Note:

  1. Only one of the options is to be filled. More than one option shall be rejected.

  2. Rate filled in any form shall be considered only in %age.

  3. Rate shall be filled both in figures and in words, otherwise tender shall be rejected

  4. Rate filled at any other place in the document shall not be considered.

  5. No condition shall be accepted.




Option

%age In Figures

In Words

Percentage below “A”







Percentage above “A”







At Par of “A”









Full Signatures of Contractor :
Name :












TENDER PROFORMA










1

Tender Ref. No.



2

Tender Title



3

Tender Value (INR if Not mentioned)



4

EMD



5

Document Cost



6

Tender Type

Work Contract

7

Location



8

Publishing date on portal

current date

9

Last date of document collection and time



10

Last date for submission and time



11

Opening date and time



12

Work Description

Sr.No

Name of Work

Amount (in lacs)

Earnnest Money (in Lacs)

Time Limit

 




 



 

 

 

 














 

 

 

 

 



 

13)

Pre -Qualification





 

 





 

 





 

 





 

 





 

 




























































































Executive Engineer(C )













Punjab Mandi Board,