Ana səhifə

Environmental Management Framework (emf) coastal embankment improvement project phase-i project (ceip-i) April 29, 2013 Dhaka Bangladesh Water Development Board Ministry of Water Resources Government of the People’s Republic of Bangladesh


Yüklə 7.67 Mb.
səhifə17/35
tarix25.06.2016
ölçüsü7.67 Mb.
1   ...   13   14   15   16   17   18   19   20   ...   35

7.6Selection of Important Environmental and social Components (IESCs), scoping and bounding


  1. Environmental and social components likely to be impacted by the project interventions are termed as Important Environmental and social Components (IESCs). IESCs have been selected based on the rationale of impact for each component during pre-construction, construction and post-construction stages. A scoping process was followed for selecting IESCs which are likely to be impacted by the proposed interventions of CEIP. Scoping was done in two stages. Individual professionals of EA study team made a preliminary list of the components pertaining to their disciplines, which could be impacted by the project. The second stage included scoping sessions where stakeholder perceptions have been obtained about those environmental and social components. Professional judgment of the EA team members as well as the stakeholder opinions obtained in the scoping sessions was considered in selecting the IESCs. Area likely to be impacted by the proposed interventions of the CEIP project was delineated in consultation with the feasibility study team members in addition to feed back received from the local people during baseline consultation and stakeholder consultation meeting. The entire area influenced by proposed sub-projects under CEIP project was considered as the potential area to be impacted.

Table 7 8 Impact of Project Activity on IESC




IESC

Pre-construction/Initial Phase

Construction/Implementation Phase

Operation Phase

Indirect effect

of operation

of induced

development

Land Acquisition

Removal

of

structures

Removal of

trees and

vegetation

Realignment of Polder

Site Selection for Afforestation

Excavation/ Earthwork

Vehicle &

machine

operation &

maintenance

River Bank protection

Dredging

Sanitation &

waste (labor

camps)

Project

operation

Air




Dust

generation

during

dismantling



Reduced

buffering of

air and noise

pollution,

hotter, drier

microclimate









Fugitive Dust generation

PMs, NOx, SOx

Dust pollution




Odour / smoke

SPMs, NOx, SOx

Other pollution

Soil/ Land













Change in land scape

Landscape will be degraded
If top soil is removed land fertility will be decreased
Disposal of dredged material at improper site
Collection of soil material for earthen work from surrounding areas may create destruction of near by structures, erosion from collection site.













Water logging

Fertility may increase due to TRM

Agriculture

Loss of agricultural land







Loss of agricultural land

Loss of agricultural land

Top soil removal
Borrow pit may induce nuisance plant growth which will effect agriculture production













Crop damage area will be decreased
Improper use of hydraulic structure operation may lead to salinity increase
If Tidal River Management is traduced flooding in the low lying areas

Irrigation area in dry season will increase
Agriculture loss due to TRM
Due to TRM salty and Brackish water from the Bay getting into agriculture land will have major negative impacts on rice cultivation and other crops which require salt free water

Water resource & Hydrology




Siltation

due to loose earth



Siltation

due to loose earth



Encroaching water bodies

Soil erosion due to wrong site selection

Siltation

due to loose earth



Contamination

by fuel and

lubricants


Siltation

due to loose earth, soil erosion



The suspended sediment load and turbidity of a river are increased

Contamination

from wastes



-Soil erosion and sedimentation mismanagement
Eutrophication in the borrow pit
May create backwater flow due to the embankment and improper use of hydraulic structure
Water logging due to TRM and improper use of hydraulic structure

Increased

contamination

of surface water


Fisheries

Encroachment of fish habitat







Encroachment of fish habitat




Increased siltation in the water bodies







Substrate removal will inevitably affect spawning.
Suspended sediment in the water affects the respiratory system of fish.
Growth may also be affected since food supply and feeding success are reduced in the turbid conditions






Hudraulic Structures will create barrier for fish migration

Reduction in fish species

Ecosystem







Loss of Biomass

Encroaching habitat




Eutrophication

Contaminating water

Barrier on free movement

Loss and alteration of natural habitat




Improper selection of plant will introduce nuisance plant

Change of Ecology

Noise



















Increase







Increase

Increase

Increase

Socio-economic

Displacement

of people

psychological

impact on

people loss of

livelihood


Effect on cultural set ups




Displacement

of people







Borrow pits can be mosquito breeding place

Damage of local roads due to movement of heavy axle loads







Increase in

communicable

diseases


Water logging will act as mosquito breeding place

TRM will greatly impact the livelihood of the people in the low lying area every year

  • Assessment Methodology




  1. The assessment of effects and identification of residual impacts takes account of any incorporated mitigation measures adopted due to any potential impact of Project activities, and will be largely dependent on the extent and duration of change, the number of people or size of the resource affected and their sensitivity to the change. Potential impacts can be both negative and positive (beneficial), and the methodology defined below will be applied to define both beneficial and adverse potential impacts.




  1. The criteria for determining significance are generally specific for each environmental and social aspect but generally the magnitude of each potential impact is defined along with the sensitivity of the receptor. Generic criteria for defining magnitude and sensitivity used for the Project are summarized below.


Magnitude


  1. The assessment of magnitude has been undertaken in two steps. Firstly the key issues associated with the Project are categorized as beneficial or adverse. Secondly, potential impacts have been categorized as major, moderate, minor or negligible based on consideration of the parameters such as:

  • Duration of the potential impact;

  • Spatial extent of the potential impact;

  • Reversibility;

  • Likelihood; and

  • Legal standards and established professional criteria.



  1. The magnitude of potential impacts of the Project has generally been identified according to the categories outlined in Table 7.2.


Table 7.9: Parameters for Determining Magnitude

Parameter

Major

Moderate

Minor

Negligible/Nil

Duration of potential impact

Long term

(more than 35 years)



Medium Term

Lifespan of the project

(5 to 15 years)


Less than project lifespan

Temporary with no detectable potential impact

Spatial extent of the potential impact

Widespread far beyond project boundaries

Beyond immediate project components, site boundaries or local area

Within project boundary

Specific location within project component or site boundaries with no detectable potential impact

Reversibility of potential impacts

Potential impact is effectively permanent, requiring considerable intervention to return to baseline

Baseline requires a year or so with some interventions to return to baseline

Baseline returns naturally or with limited intervention within a few months

Baseline remains constant

Legal standards and established professional criteria


Breaches national standards and or international guidelines/obligations

Complies with limits given in national standards but breaches international lender guidelines in one or more parameters

Meets minimum national standard limits or international guidelines

Not applicable

Likelihood of potential impacts occurring

Occurs under typical operating or construction conditions

(Certain)



Occurs under worst case (negative impact) or best case (positive impact) operating conditions (Likely)

Occurs under abnormal, exceptional or emergency conditions (occasional)

Unlikely to occur

Sensitivity


  1. The sensitivity of a receptor has been determined based on review of the population (including proximity / numbers / vulnerability) and presence of features on the site or the surrounding area. Criteria for determining receptor sensitivity of the Project’s potential impacts are outlined in Table 7.3.


Table 7.10: Criteria for Determining Sensitivity

Sensitivity Determination

Definition

Very High

Vulnerable receptor with little or no capacity to absorb proposed changes or minimal opportunities for mitigation.

High

Vulnerable receptor with little or no capacity to absorb proposed changes or limited opportunities for mitigation.

Medium

Vulnerable receptor with some capacity to absorb proposed changes or moderate opportunities for mitigation

Low / Negligible

Vulnerable receptor with good capacity to absorb proposed changes or/and good opportunities for mitigation

Assigning Significance


  1. Following the assessment of magnitude, the quality and sensitivity of the receiving environment or potential receptor has been determined and the significance of each potential impact established using the potential impact significance matrix shown in Table 7.4.

Table 7.11: Assessment of Potential Impact Significance

Magnitude of Potential impact

Sensitivity of Receptors

Very High

High

Medium

Low / Negligible

Major

Critical

Major

Moderate

Negligible

Moderate

Major

Major

Moderate

Negligible

Minor

Moderate

Moderate

Low

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible



1   ...   13   14   15   16   17   18   19   20   ...   35


Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©atelim.com 2016
rəhbərliyinə müraciət