Our ref: FBC/05/2332/C/W
Your Ref: S/2008/0630/F & S/2009/0579
17 March 2011
Ms S McEvoy

Special Studies Unit

The Planning Service Headquarters

Millennium House

17-25 Great Victoria Street

Belfast


BT2 7BN

Dear Ms McEvoy


Further Information and Clarification of Environmental Statement and Supporting Documents

Proposed Biomass Fuelled Power Plant – Planning Application Ref S/2008/0630/F

Site off Ballyvannon Road, near Glenavy, Co. Antrim

Water Abstraction Facility & Water Pipeline – Planning Application Ref: S/2009/0579

Land opposite 20 Shore Road, part Shore Road and Ingrams Road

For Rose Energy Ltd
Further to our letter and that from our client’s solicitors, Arthur Cox, both dated 10th March, 2011, we enclose 25 copies a single revised CD incorporating all of the previously submitted documents but where all signatures from the documents have been redacted. We trust that this will enable you to upload the documents on to the Department’s public access website.

To avoid confusion the updated CD has a predominately red coloured title.

The documents on each CD are as follows:


  • 01. Welcome page

  • 02. Report on a Winter Bat Survey of Trees, Hopkirk and Russ Bat Ecology, Feb 2010

  • 03. Smooth Newt (Lissotriton vulgaris) Survey, Ecological Management Group, May 2010

  • 04. Baseline assessment of the aquatic ecology of the lower Glenavy River: Final Report July, 2010, Queen’s University Belfast

Cont/...


2.

Ms S McEvoy

Special Studies Unit

The Planning Service Headquarters



Further Information and Clarification of Environmental Statement and Supporting Documents

Proposed Biomass Fuelled Power Plant – Planning Application Ref S/2008/0630/F

Site off Ballyvannon Road, near Glenavy, Co. Antrim

Water Abstraction Facility & Water Pipeline – Planning Application Ref: S/2009/0579

Land opposite 20 Shore Road, part Shore Road and Ingrams Road

For Rose Energy Ltd



  • 05. Information for an Appropriate Assessment of the impacts on Lough Neagh and Lough Beg SPA / Ramsar site pursuant to regulation 43(2) of the Conservation (Natural Habitats &c.) Regulations (Northern Ireland) 1995, Ecology Solutions, March 2011

  • 06. NIE Grid Connection – Clarification, GBPP Ltd, March 2011

  • 07. ES Chapter 15, Ecology and Nature Conservation

  • 08. ES Addendum, NTS Amendments

Rose Energy has a website where these further submissions can be viewed and also downloaded – see www.roseenergy.co.uk. Copies of the documents are also available on CD at a cost of £15 and printed copies at a price of £100. CD copies or printed copies can be purchased from Glenconway House, 31 Ballyvannon Road, Glenavy, Crumlin, Co Antrim, BT29 4QJ (contact Heather McKinstry on 02894 451 885); cheques should be made payable to Rose Energy Ltd. Alternatively, copies on CD or printed versions can be obtained by writing to The Graham Bolton Planning Partnership Limited at Onward Buildings, 207 Deansgate, Manchester M3 3NW; a cheque should be enclosed with the request in writing, made payable to Graham Bolton Planning.

Please do not hesitate to contact either Graham Bolton or Fiona Child if you have any queries, or wish to discuss any aspect of this further information. We appreciate that new information will be advertised and sent to your consultees and we request that you inform us of the timetable for that exercise.
Yours sincerely

Graham Bolton Planning
Enc


fbc@gbpp-planning.co.uk
Our ref: FBC/05/2332/C/W
Your Ref: S/2008/0630/F & S/2009/0579
17 March 2011

Ms S McEvoy

Special Studies Unit

The Planning Service Headquarters

Millennium House

17-25 Great Victoria Street

Belfast

BT2 7BN



Dear Ms McEvoy
Further Information and Clarification of Environmental Statement and Supporting Documents

Proposed Biomass Fuelled Power Plant – Planning Application Ref S/2008/0630/F

Site off Ballyvannon Road, near Glenavy, Co. Antrim

Water Abstraction Facility & Water Pipeline – Planning Application Ref: S/2009/0579

Land opposite 20 Shore Road, part Shore Road and Ingrams Road

For Rose Energy Ltd
Further to our letter and that from our client’s solicitors, Arthur Cox, both dated 10th March, 2011, we enclose 25 copies a single revised CD incorporating all of the previously submitted documents but where all signatures from the documents have been redacted. We trust that this will enable you to upload the documents on to the Department’s public access website.

To avoid confusion the updated CD has a predominately red coloured title.

The documents on each CD are as follows:


  • 01. Welcome page

  • 02. Report on a Winter Bat Survey of Trees, Hopkirk and Russ Bat Ecology, Feb 2010

  • 03. Smooth Newt (Lissotriton vulgaris) Survey, Ecological Management Group, May 2010

  • 04. Baseline assessment of the aquatic ecology of the lower Glenavy River: Final Report July, 2010, Queen’s University Belfast

  • 05. Information for an Appropriate Assessment of the impacts on Lough Neagh and Lough Beg SPA / Ramsar site pursuant to regulation 43(2) of the Conservation (Natural Habitats &c.) Regulations (Northern Ireland) 1995, Ecology Solutions, March 2011

  • 06. NIE Grid Connection – Clarification, GBPP Ltd, March 2011

  • 07. ES Chapter 15, Ecology and Nature Conservation

  • 08. ES Addendum, NTS Amendments

Rose Energy has a website where these further submissions can be viewed and also downloaded – see www.roseenergy.co.uk. Copies of the documents are also available on CD at a cost of £15 and printed copies at a price of £100. CD copies or printed copies can be purchased from Glenconway House, 31 Ballyvannon Road, Glenavy, Crumlin, Co Antrim, BT29 4QJ (contact Heather McKinstry on 02894 451 885); cheques should be made payable to Rose Energy Ltd. Alternatively, copies on CD or printed versions can be obtained by writing to The Graham Bolton Planning Partnership Limited at Onward Buildings, 207 Deansgate, Manchester M3 3NW; a cheque should be enclosed with the request in writing, made payable to Graham Bolton Planning.



Please do not hesitate to contact either Graham Bolton or Fiona Child if you have any queries, or wish to discuss any aspect of this further information. We appreciate that new information will be advertised and sent to your consultees and we request that you inform us of the timetable for that exercise.
Yours sincerely

Graham Bolton Planning
Enc